Before asking for a commercial battery size, export the site’s electricity data at the finest useful interval available. Include the timestamps and units exactly as recorded. A monthly bill is useful for checking totals, but it cannot show how long a factory peak lasts or when the battery could recharge.

You do not need a polished report to start. A clearly labeled CSV, a tariff document and a short explanation of the site’s operating hours usually give the engineer a much better starting point than a proposed cabinet size.

Get the measurement boundary right

Identify the meter whose readings you are sending. Is it at the grid connection, on a production line or downstream of existing solar?

Grid import after solar generation is different from the building’s total consumption. If the project model expects total load and receives net import instead, adding the solar profile again can count its contribution twice.

Where possible, provide separate import, export and solar-generation records. If only one signed channel is available, explain which sign means import. Keep the original export as a reference and make any cleaned version a separate file.

The SAM Electric Load documentation accepts hourly or subhourly time-series inputs and treats critical loads separately for outage analysis. The project’s modeling tool will have its own import format, so preserve the source information before adapting it.

Factory load-data planning desk with a storage cabinet

Label the columns so another person can use them

Column or accompanying note Example of useful information
Timestamp Local timestamp with a stated time zone or UTC offset
Interval convention Reading covers the period ending at the timestamp
Interval length 15 minutes
Measurement Average import power in kW, or interval energy in kWh
Meter location Main grid connection, downstream of existing PV
Data quality Measured, missing, estimated or affected by an outage

Download the blank load-data worksheet if you need a place to organize the readings. It includes a quality flag so a missing interval does not have to be disguised as zero consumption.

A 15-minute energy reading of 25 kWh corresponds to 100 kW average power over that interval: 25 ÷ 0.25 = 100. Entering 25 as kW would understate the average power by a factor of four. Conversely, a kW channel should not be divided by the interval again.

Keep the awkward days

Include shutdowns, unusually busy days and weather-related changes in production. Those periods can affect whether a proposed battery has enough time to recharge or enough energy for an extended peak.

A full year is a useful target when available because it captures seasonal operation. If you only have a shorter record, state the dates and describe what is missing. The engineer can assess a preliminary case and identify where more data would change the result.

Check for duplicate timestamps, gaps and daylight-saving changes. A simple graph often reveals an unexplained flat line or a missing day. Compare the sum of interval energy with the bill for the same meter and period; investigate material differences before using the file for a savings estimate.

Avoid filling every gap by interpolation. A gap during a production peak can affect sizing more than a gap during a quiet night. Keep the quality flag and explain the treatment.

Add the tariff and planned changes

The tariff document should include time-of-use periods, demand-charge rules and the relevant billing interval. If export compensation applies, include that as well. The load shifting and peak shaving article explains why these objectives lead to different battery duties.

Tell the engineer about planned changes: an extra shift, a new production line, EV charging or a solar extension. Send the expected timing and load where known. Historical data cannot represent equipment that has not yet been installed.

Backup requirements need a separate load list. The whole site’s consumption may include equipment the owner is willing to stop during an outage.

Send a package that can be quoted

For the first review, attach the original meter export, your labeled worksheet, the tariff and a one-page site note. Include the AC voltage and phase arrangement, import/export constraints and the required backup reserve.

LAINERGY’s commercial storage range includes different power-to-energy ratios. With the load record, the quotation can compare suitable configurations against the site’s discharge and recharge windows. Send the package through the project inquiry form and ask which assumptions still affect the proposed size.